LAC + USC Core Lab Equipment Replacement
/LCDG is currently performing construction administration services for the Core Laboratory Equipment Replacement project at the
LAC + USC Medical Campus. This lab is one of the biggest of its kind in the western Unites States. The new state-of-the-art equipment will place the facility at the front of medical industry.
The project consists of six phases, each introducing new equipment in a planned and well thought-out sequence. New flooring and ceilings are installed within the area of work, and new workstations are provided to meet the lab’s growing needs. Staff offices and conference rooms are reconfigured to provide additional space. Project completion must occur before the end of 2017 to insure timely transition to new compounds used in the lab processing.